Segment 4 of SH 130 Now Open!
The portion of SH 130 from SH 71 south to US 183 near Mustang Ridge will opened on April 30, 2008.
- Click here to read the press release from TxDOT

Above: Bob Daigh speaks at the Segment 4 ribbon cutting ceremony on Wednesday, April 30, 2008.

Above: LSI Management, TxDOT officials and local elected representatives cut the ribbon opening Segment 4 of SH 130.
For information regarding Segments 5 and 6, spanning from US 183 near Mustang Ridge to I-10 in Seguin, please visit www.mysh130.com.
What segments of SH 130 are open?
Curious about which segments of SH 130 are open as of June, 2007? Look no further than right here:
Segment 1 (I-35 north of Georgetown to US 79 in Hutto)
Segment 2 (US 79 in Hutto to US 290 east of Austin)
Segment 3 (US 290 to Texas 71 at Austin Bergstrom Int'l Airport)
Segment 4 (Texas 71 to US 183 north of Mustang Ridge)
Click here to see a map of the above segments.
|